Ev ve Endüstriyel PPR Boru Kurulum Kılavuzu
In the global wave of building water supply system upgrades, PPR (rastgele kopolimer polipropilen) borular are gradually replacing traditional metal pipes with their high temperature resistance, corrosion resistance and zero leakage characteristics. As a professional exporter who has been working in the pipeline industry for 10 yıllar, Let us reveals the PPR pipe standard installation process for you to help you create a reliable pipeline system with 50 years of maintenance free.

Birinci,Industrial and Home use PPR Pipeline Aavantajlar (Required reading before construction)
1. Malzeme Characteristics
Operating temperature range: -20 °C ila 95 °C (better than the upper limit of 60 ° C of PVC pipe)
Compressive strength: 2.5MPa at 20℃ environment (through ISO 9001 sertifikasyon)
Sanitary rating: NSF/ANSI 61 Drinking water system certification
2. Economic Comparison
| Boru hattı türü | Installation cost | Maintenance cycle | Servis ömrü |
| Galvanizli çelik boru | high | 3-5 yıllar | 15 yıllar |
| Copper pipe | Extremely high | 8-10 yıllar | 25 yıllar |
| PPR tube | Orta | Maintenance-free | 50 yıllar |
Professional grade PPR tube installation 7-step method
Step 1: Accurate mapping and cutting
Use a laser rangefinder to ensure ±2mm accuracy
Cutting tool selection:
Rotary cutter (DN20-DN63 pipe diameter)
Electric pipe cutter (DN75 + large diameter pipe)

Step 2: Key technologies of hot melt welding
Temperature control: 260±5℃ (equipped with digital temperature control welding machine)
Heating time reference table:
| Boru çapı (mm) | Heating time (S) | Engaging time (S) | Soğutma süresi (min) |
| 20 | 5 | 4 | 2 |
| 32 | 8 | 6 | 4 |
| 63 | 24 | 8 | 6 |
Step 3: Pipe fixing points
Pipe clamp spacing standard:
Horizontal pipe: DN20 pipe @600mm
Vertical tube: DN32 tube @1200mm
304 stainless steel spring clamps are recommended
5 Solutions to common installation problems
1. Virtual welding problem diagnosis
Cause: pipe/fittings are not clean, insufficient heating time
Rapid detection method: 30° bending test after welding
2. Winter construction precautions
When the ambient temperature is < 5°C, the cooling time is extended by 50%
Use [brand name] low temperature special PPR tube (glass transition temperature -15℃)
3. Lintel sleeve installation specifications
Casing diameter ≥ pipe outer diameter +20mm
Fill with flexible flame retardant material for seal
4.Professional tool set recommended
Intelligent temperature control welding machine: with temperature compensation function
Multifunctional pipe cutter: Support 20-110mm full specification
Pipe detector: can measure the depth of welding penetration

5.How to choose PPR pipeline?
1. High quality raw materials
The Nordic chemical RA130E raw material is used, the ash content is < 0.02%
2. Global certification system
It has obtained 28 international certifications such as CE, WRAS and SGS
Tedarikçi
Luoyang Datang Enerji Teknolojileri A.Ş., Ltd.. yüksek kaliteli plastik boru ve bağlantı parçaları konusunda uzmanlaşmış lider bir Çinli üreticidir. Son teknoloji otomatik üretim hatlarıyla donatılmış ve bir ekip tarafından desteklenen 200 profesyoneller, aşağıdakileri içeren kapsamlı bir ürün yelpazesi sunuyoruz: 150 types of plastic pipes and fittings designed for water supply and drainage systems, gaz iletimi, ve yerden ısıtma sistemleri. Ana ürünlerimiz arasında PVC Borular ve Ek Parçaları, PE (HDPE) Borular ve Ek Parçaları, PPR Boru ve Ek Parçaları, ve PEX Yerden Isıtma Boruları.
Bizimle ilgili herhangi bir sorunuz varsa Sağlıklı PPR Boru ve Ek Parçaları, lütfen bizimle iletişime geçmekten çekinmeyin!
Tel.:0086-183 3790 0677
Wechat: 0086-183 3790 0677
Whatsapp: 0086-183 3790 0677
E-posta: sales@pipesandfittings.net